PAGOTE TO CHOWK TUNNEL

PAGOTE TO CHOWK TUNNEL

Authority:National Highway Authority of India (NHAI)
Client:TPF Engineering Pvt Ltd.
Location:Maharashtra, (India)
Project Name

Consultancy services for Preparation of DPR for development of Economic Corridors, Inter Corridors, Feeder Routes and Coastal roads to improve the efficiency of freight movement in India (Lot-1/Maharashtra/Package-3) – Pagote to Chowk

Project Overview:

Pagote to Chowk Project alignment begins near Pagote village at Ch.0+100 and ends at Chowk on NH-48 Ch.29+319 . Total Length of the Project is 29.219 Kms. Along the proposed alignment there are 2 nos. Twin Tunnels proposed, details are as below,

  • Tunnel 1 = 1900m Approx Length
  • Tunnel 2 = 1568m Approx Length
Scope of Work

Consultancy service for Preparation of feasibility study & detailed project report for Pagote to Chowk Project. Our services include:

  • Geological Mapping and Surveys along with analysis and detailed report conforming to requirements of IRC: SP:91-2010 and with derivation of parameters required for Tunnel Design and Protection measures.
  • Review the available Geotechnical Investigations and suggest required extents and type of Geotechnical Investigations required.
  • Design of Tunnel including Portals, Protection measures such as Lining, etc., based on available data of similar projects (e.g., Pune Ring Road).
  • Preparation of tender documents as part of the EPC Contract, including:
    • Schedules
    • Material specifications report
    • Typical layout & cross-section drawings
    • Bill of Quantities (BOQ) for tunnels and associated structures
  • Site visits.
  • Providing assistance during the tender stage.
Project duration – 2024 – 2025