MUMBAI COASTAL ROAD PROJECT

Project Name:Mumbai Costal Road Project – Package IV
Authority:Municipal Corporation of Greater Mumbai
Client:Lombardi Engineering Group
Location:Mumbai, Maharashtra (India)
Project Overview
  • The Mumbai Coastal Road features a submerged tunnel in Package IV.
  • The tunnel consists of a 3,000 m long twin tube with two lanes and an emergency lane (expanded to three lanes during high traffic intensity).
  • It includes cross passages every 300 m and one pump shaft.
  • For excavation, a Hydro shield-TBM will be used.
  • The road is situated approximately 22 m below sea level.
  • Beneath Malabar Hill, the overburden at the crown reaches up to 70 m (along the shore).
  • The tunnel intrados has a diameter of 11 m and utilizes precast segments (referred to as “universal segments”).
  • Prefabricated, walkable technical canals are present at each invert.
  • The cut & cover intrados section measures 11 x 6.5 meters.
  • Ramps connect the project to the bridge viaducts in the north and the existing road network in the south, along Marine Drive.
About Technical Building
  • Location: The building is situated on top of a cut and cover section of LHS, with a portion integrated into it.
  • Structure Division: It is divided into two parts: one above the cut and cover box and the other housing a CNC system.
  • Purpose: The building provides dedicated electrical and mechanical services to meet the technical/engineering requirements of the tunnel beneath.
  • Levels:
    • Ground Level: Access to the technical room below and standby fire vehicles. Landscaping is proposed around and above the deck/slab. Features include a dedicated ventilation system (Saccardo Equipment), battery room, LV panel room, MV panel room, transformer room, training room, office, toilets, staircase, and approach shaft.
Scope of Work
Design of Underground Technical Building for Mumbai Coastal Road Project.
  • Review & assessment of proposed building
  • Suggest necessary changes and resolve constructability issues
  • Design of Underground Technical Building (North & South)
  • Existing Cut & Cover Box Design adequacy check
  • Technical clarifications for Approval
Project duration – 2021 to 2022

DELHI METRO PHASE IV

Authority:Delhi Metro Rail Corporation (DMRC)
Location:Delhi (India)
Scope of Work
Sub-consultancy Engineering services for detail design of Temporary structures for stations include:
  • Design of Temporary Strutting System
    • For Underground Metro Station
  • Gantry Girder and Support Design
    • For Underground Metro Station
  • Rock Slope Stability Analysis & Design
  • 3D modelling and Analysis
  • Design Optimization
  • Getting approval from GC/Contractor
Project duration – 2023 to 2024

PATNA METRO

Authority:Delhi Metro Rail Corporation Limited
Client:Assystem Stup
Contractor:SAM India-STEC JV
Location:Patna, Bihar (India)
Project Overview

Contract PC-06: Design & Construction of Twin Tunnel by Shield TBM, Tunnel by Cut & Cover, Underground Ramp at Rukanpura and Three Underground Metro Stations namely Rukanpura, Raja Bazar & Patna Zoo. This includes Architectural Finishing, Water Supply, Sanitary Installation & Drainage Works of Stations on Danapur to Khemnichak Corridor 1 of Phase-I of Patna MRTS

Project Overview:
  • TBM Tunnel : 3885m (Twin Tunnel)
  • Station (3 No’s) : Rukanpura (160m), RajaBazar (160m) & Patna Zoo Station (355m)
  • Ramp : 145 m
  • C&C Tunnel : 206 m
Scope of Work
Pre-bid Engineering services for Patna Metro Contract PC-06 Corridor 1 of Phase-I include:
  • Review of Tender documents
  • Geotechnical Appreciation report
  • Preliminary Design of TBM Tunnel & associated structures (CPs)
  • Design calculations and methodology for tunneling under existing railway tracks and adjacent structures
  • Ground Improvement Methodology
  • Instrumentation and monitoring scheme
  • Proposal for strengthening adjacent structures
  • Likely construction methods
  • Assessment of site constraints
  • Bill of Quantities (BOQ) for Tunnel & associated structures (CPs)
  • Sketches/Preliminary Drawings for Tunnels & associated structures (CPs) required for Prebid submission
  • Building Damage Assessment
  • Site visit
Project duration – 2024

PHILIPPINES METRO

Project:Philippines North South Rail Corridor CP S02 Package
Authority:Department of Transportation, Philippine National Railways
Client:Gülermak Ağir Sanayi İnşaat Ve Taahhüt A.Ş. & Doğuş Construction and Trade Inc
Location:Philippines
Project Overview:
  • The North-South Commuter Railway Project (South Line) connects the PNR Solis Station in Tondo, Manila, to the PNR Calamba Station in Laguna.
  • The total length of the railway is approximately 56 kilometers.
  • There are a total of nineteen (19) stations along this route.
Project Structure:
  • The project is divided into seven packages.
  • CP S02 is a significant part of this stretch and includes the following features:
    • This stretch includes a 7.91 km elevated viaduct railway corridor.
    • Seventeen (17) bridges, including:
      • Steel box girders
      • Balanced cantilevers
      • U-bridges
      • Cast-in-situ bridges
        • Double-track operation capability.
        • Three elevated stations.
Scope of Work
Prebid Engineering services for Elevated Viaduct & Metro Stations, CP S02 Package. Our services include;
  • Quantity survey for civil works including viaducts and stations.
  • Drainage works
  • Road works
  • Station’s Architectural & Finishing works
  • Landscape works
Project duration – 2020 to 2021

SURAT METRO

Authority:Gujarat Metro Rail Corporation Limited
Client:RINA
Location:Surat, Gujarat (India)
Scope of Work
Lead Design Checker for Tunnels & associated structures for Surat Metro Rail Project, PH-1/UG-2/PKG-CS3
  • Temporary & Permanent Structures of TBM Tunnel
  • Cross-Passage & Ramps
  • MEP & Ventilation
Project duration – 2022 to 2024

RIYADH METRO

Authority:High Commission for The Development of Riyadh
Client:Bureau Veritas, KSA
Location:Riyadh, Saudi Arabia
Project Overview:
  • The Riyadh Metro is an urban rapid transit project in Riyadh, Saudi Arabia.
  • It is part of the Riyadh public transportation system, which is one of the largest public transport projects in the country.
  • The metro system spans a total length of 176 km and includes six lines.
  • There are a total of 85 stations across the network.
Scope of Our Package:
  • Independent Checking Engineer responsibilities cover various segments:
    • Elevated Section (Viaduct Culvert): 12.5 km
    • TBM Tunnel: 16 km (9.2 m diameter, 20 m deep)
    • NATM (New Austrian Tunneling Method): 2 km
    • At-Grade Section: 15 km
    • Deep Underground Stations: 15
    • At-Grade Stations: 4
    • Shallow Stations: 6
    • Elevated Stations: 11
    • Transfer & Interchange Stations: 7
Scope of Work

Full Shop Drawing Review for Riyadh Metro Package 1. Our services include:

  • Shop Drawing Review:
    • Review of all contractor’s shop drawings and stamping for Line 1 & 2.
    • Identify discrepancies and non-compliances.
    • Report findings to the Contractor.
  • Means and Methods Review:
    • Assess the Contractor’s selected means and methods.
  • Monthly Reporting:
    • Issue monthly reports highlighting discrepancies and non-compliances.
  • Additional Services:
    • Ground Remediation
    • Traffic Impact Assessments
    • Utilities Management (Isolations, Diversions, and Protection)
    • Utilization of Structural Engineering, Geotechnics, Drainage, Railway, and Metro Engineering
    • Design, Risk Management, and Quality Assurance
    • Aconex Document Management System for Retrieval and Transmittal
    • Review of Management Plans, Work Processes, Tools, and Software
Achievement
  • Reviewed and approved 70000 shops and fabrication drawings with 18 months period. Enhance profitability of client (5X) by outsourcing to Bouw.
Project duration – 2019 to 2021

CHENNAI METRO

Project Name:Chennai Metro Phase 2
Authority:Chennai Metro Rail Limited (CMRL)
Client:China Rail Tunnel Group (CRTG)
Location:Chennai, Tamil Nadu (India)
Scope of Work
Pre-Bid Engineering Services for Chennai Metro Rail Project, Phase 2 Pkg. CP30/UT01 & UT02.
  • Tender Documents Review for Design Requirements
  • Preliminary Design for Temporary Structures
  • Review of Geological, Geotechnical, Building Condition Survey Reports
  • Quantity Estimation
  • Ground Investigation Proposal, Dewatering Note, Methodology, Ground Improvements, GIR
  • Outline Design Criteria & Construction Specifications
  • Preliminary Construction Methodology
  • Construction Impact Assessment/Building Damage Assessment
  • Specifications, Design Methodology & Manual
  • Preliminary Instrumentation & Monitoring Plan & Report
  • Preliminary Traffic Management Plan
Project duration – 2019 to 2020

Mumbai Metro Line 3

Authority:Mumbai Metro Rail Corporation Limited (MMRC)
Location:Mumbai, Maharashtra (India)
Scope of Work
Design of Cross Over for Mumbai Metro Line 3
  • Design of Temporary Strutting System
  • Rock Slope Stability Analysis & Design
  • Settlement & Seepage Analysis
  • 3D Modelling and Analysis
  • Design of Permanent Structures for Cut & Cover
  • Instrumentation and Monitoring Scheme
  • Design Optimization
  • BOQ Preparation
  • Getting Approval from GC/Contractor
Achievement
  • Cost optimization in Temporary Strutting System 30%. Used available built-up section about 15%.
Project duration – 2019 to 2021